27th Street, Holdrege Street to Fletcher Avenue Concrete Pavement Repair Project

March 2017

Concrete repairs will begin soon along 27th Street between Holdrege Street and Fletcher Avenue. Construction is scheduled to begin April 17, 2017 and be completed by November 4, 2017.

Translated Fact Sheet
Tiếng Việt PDF (Vietnamese)

Preliminary Plan Not Final – Subject to Change

  • Project Area

Re-center mapFull-screen

Purpose and Need

This is a pavement preservation project intended to maintain and improve the driving surface of the existing roadway facility. The need for the improvement is based upon information from the City of Lincoln’s Pavement Management System (overall condition rating) and visual inspections by City staff.

Scope of Work

The project consists of replacing and/or repairing concrete panels, joints, median surfacing, curbs, and curb inlets within the street that are deteriorated. Areas of the project with asphalt paving will be replaced with full depth concrete.

Access During Construction

Work will be completed under lane closures, allowing 27th Street to stay open during construction. Due to the location of the repairs, there may be times when turn lanes are closed. Access to businsses and residences will be maintained but may be limited at times. Pedestrians and bicyclists may be directed to alternate crossings while repairs are made in crosswalks.

Anticipated Schedule

Right-of-Way

All work is anticipated to take place within existing right-of-way and easements.

Wetlands

Impacts to wetlands are not anticipated.

Traffic Volume Estimates:

27th Street, Holdrege to Fletcher
Year 2015 2025
Vehicles Per Day: 31,000 34,200
Percentage Trucks: 0.5% 0.5%

Estimated Cost of the Project

This pavement preservation project is eligible to receive 80 percent federal funding for construction and construction engineering, with a 20 percent local funding match. The cost of the proposed project is approximately $3.9 million and would derive from federal and local funding sources.

Public Involvement

Pre-Construction Open House – April 6, 2017
5:30 to 7 p.m.
Salvation Army, 2625 Potter Street (use northeast entrance)
Meeting Invitation PDF | Tiếng Việt PDF (Vietnamese) | Meeting Handout PDF (bilingual)

Project Contacts

  • Lance Murry, Construction Project Manager

    Olsson Associates
    402-458-5638

  • Zach Becker, Project Engineer

    City of Lincoln, Engineering Services
    402-613-3763
    Email: zbecker@lincoln.ne.gov

  • Steve Ragoss, Project Contractor

    TCW Construction, Inc.
    Phone: 402-475-5030