66th and Fremont Intersection Improvement Project

Scope of Work

This project was designed to increase safety at the intersection of 66th and Fremont by adding a roundabout, ADA-accessible sidewalks and street lights.

Schedule

Construction began June 4, 2018, and the intersection opened to traffic August 22, 2018.

Access During Construction

The intersection of 66th and Fremont was closed throughout construction. Access to adjacent properties was maintained except during driveway reconstruction. The detour route included 70th, Adams, and 56th.

Public Involvement

Open House - Tuesday, May 22, 2018
5:00 to 6:30 p.m.
Anderson Branch Library
3635 Touzalin Avenue
Open House Handout (370 K) PDF

Project Contact

  • Jess Sundeen, Construction Project Manager

    City of Lincoln, Engineering Services
    Phone: 402-416-5341
    Email: jsundeen@lincoln.ne.gov

  • Zach Becker, Project Engineer

    City of Lincoln, Engineering Services
    Phone: 402-613-3763
    Email: zbecker@lincoln.ne.gov

  • Steve Ragoss, Project Manager

    MTZ Construction
    Phone: 402-430-3431
    Email: steve.mtzllc@gmail.com