70th from Van Dorn to Eastborough - Pavement Repair Project

The City of Lincoln began construction the week of June 22, 2015 on a concrete pavement repair and pedestrian signal replacement project along 70th Street between Van Dorn Street and Eastborough Lane.

Project Area

  • Project Area
  • Pedestrian signal replacement

PDF Version of Aerial Overview Map  (841 K) PDF

Project Update

September 3, 2015

Work on S 70th St. between Van Dorn St. and "O" St. continues as a part of the 70th St. Repair Project. Currently there are three crews working on the project in different areas with a number of lane shifts to be aware of. Throughout the duration of the project all businesses and residences are accessible to motorists. There may be times when pavement repair needs to occur in front of a driveway or in a turn lane. When this occurs the Contractor will not perform work in front of the other access points at that time.

The south work crew is completing repair on the inside-lanes, for both northbound and southbound traffic, between Van Dorn St. and South St. The middle work crew is completing repair on the outside-lanes, for both northbound and southbound traffic, from Sumner St. to just north of "A" St. The north crew is completing repair on the inside-lanes, for both northbound and southbound traffic, between South Wedgewood Drive and "O" Street. None of the intersections within the work zones are impacted at this time. Please be aware that the open driving lane changes between outside and inside lanes while traveling through the project – signage is in place to alert motorists of which lane they should expect to be closed. Please remain alert for the workers and equipment in the area and be aware of the reduced speeds within the work zones.

Intent of Project

This is a pavement preservation project intended to maintain and improve the driving surface of the existing roadway facility. The need for the improvement is based upon information from the City of Lincoln's Pavement Management System (overall condition rating) and visual inspections by City staff. The existing pedestrian signal near 70th Street and Lincolnshire Road is reaching the end of its useful life and needs to be replaced. Pedestrian curb ramps that do not meet current Federal and local standards would be reconstructed to meet those standards.

Scope of Work

Construction will include repairing or removing and replacing deteriorated concrete panels, joints and curbs; and sealing cracks. Other work includes removing and replacing damaged storm sewer inlet tops, curb ramps that do not meet Federal and local standards, and the existing pedestrian crossing signal near 70th Street and Lincolnshire Road. Grinding of the pavement to remove irregularities and to improve smoothness will also be included with the project.

Estimated Construction Schedule

Construction will begin the week of June 22, 2015 and be completed by October 2016. All lanes will be open during the winter months.

Proposed Accommodation of Traffic During Construction

The City intends to complete the majority of the work using lane closures, allowing 70th Street to stay open during construction. However, to accommodate access needs or expedite completion of the work, there may be times when the contractor will be allowed to temporarily close portions of 70th Street and/or intersecting streets overnight to complete specific repairs, as determined by pavement conditions at the time of construction. “A” Street will be closed at the 70th Street intersection for three days for intersection repairs; however, 70th Street will remain open. Traffic will be temporarily detoured during those times but emergency access will be maintained at all times. Access to businesses and residences will be maintained but may be limited at times. Pedestrians and bicyclists may be directed to alternate crossings while the pedestrian signal is out of service, while repairs are made in crosswalks and during curb ramp reconstruction at sidewalks and bike paths.

Right-of-Way

All work is anticipated to take place within existing right-of-way and easements.

Public Involvement

Open House - Thursday, June 11, 2015
5:00 – 7:00 p.m.
Morley Elementary, 6800 Monterey Drive
Open house materials: Meeting Handout  (199 K) PDFComment Card  (354 K) PDF
Project Advisory - June 17, 2015  (237 K) PDF
Project Information Mailer - November 2013  (204 K) PDF

Contact Us

Related

Coping with Construction - A Guide for Lincoln Businesses