Public Works & Utilities Construction Projects

Project start and completion dates are estimates. Information subject to change.

10th and Salt Creek Bridge Project

10th & Salt Creek Bridge

Bridge Replacement Project

A recent structural evaluation has determined that the bridge would need to be replaced in order to meet the City of Lincoln's current and future vehicular and pedestrian needs. This project will include removing the existing bridge and constructing a new bridge at the current location.

  • Start: May 8, 2017
  • Completion: Mid-2018

Go

14th and Superior Roundabout

14th and Superior

Permanent Safety Improvements

This project includes replacing the temporary traffic control changes at the 14th and Superior roundabout with more permanent traffic control features. Thanks to a public-private partnership, the total investment will not only include concrete, turf, and trees, but also live plants, native grasses and other decorative items.

  • Start: May 2, 2017
  • Completion: Late-Jul. 2017

Go

16th Street from "A" to "F"

Roadway Reconstruction Project

This project provides much needed road repairs and will improve conditions of 16th St. between "A" and "F" streets.

  • Start: Mar 1, 2017
  • Completion: Aug. 2017

Go

27th from Calvert to Laurel

Water Service Relocation Project

This project will include the transfer of property service lines, the abandonment of existing 6” water mains, and the installation of a new 6” water main.

  • Start: Jul. 24, 2017
  • Completion: 4 weeks

Go

27th from Holdrege to Fletcher

Concrete Pavement Repair Project

The project consists of replacing and/or repairing concrete panels, joints, median surfacing, curbs, and curb inlets within the street that are deteriorated. Areas of the project with asphalt paving will be replaced with full depth concrete.

  • Start: Apr 17, 2017
  • Completion: Nov. 2017

Go

33rd from Holdrege to Madison

Mill, Overlay and Storm Drainage Improvements

The planned construction will include repairing or replacing deteriorated concrete base, curb, milling and replacing the asphalt surface. Other work includes replacing damaged storm drainage structures and inlet tops, impacted sidewalks, and reconstructing curb ramps.

  • Start: Jun. 19, 2017
  • Completion: Mid-Oct. 2017

Go

53rd and Sumner Area

Water Main Replacement Project

General Excavating will begin construction to replace the water main along Sumner and Oldham St. from 53rd to 56th. They will also be working on 53rd St. from Oldham to Sumner and 56th St. from Franklin to Oldham St.

  • Start: Jun. 12, 2017
  • Completion: Sep. 2017

Go

W Avon and Lancaster Area

Water Main Replacement Project

Work will begin Monday, July 10, to replace the water main along West Avon Lane from Vine Street to Colony Lane, in addition to an intersecting water main line on Lancaster Lane from West Avon Lane to East Avon Lane.

  • Start: Jul. 10, 2017
  • Completion: 12 weeks

Go

Coddington and West Van Dorn

Safety Improvement Project

The purpose of this project is to reduce vehicle crashes by significantly reducing the number of conflict points at the intersection. A single-lane roundabout will be constructed within the intersection. The project includes the phased construction of new concrete pavement, trails, sidewalks and box culvert extensions; the installation of a new storm drainage system; and new signage, pavement markings and street lighting.

  • Start: Apr 24, 2017
  • Completion: Oct 2017

Go

Fremont from Touzalin to 70th

Water Main Replacement Project

This project will replace the water main along Fremont Street from Touzalin to 70th.

  • Start: May 15, 2017
  • Completion: Sep. 2017

Go

Nance and “D” Area

Water Main Replacement Projects

The Public Works and Utilities Department began two water main replacement projects in February 2017: Nance Avenue from 8th to 12th streets and “D” Street from 12th to 20th streets.

  • Start: Feb 20, 2017 / Feb 27, 2017
  • Completion: 12 weeks / 24 weeks

Go

Old Cheney from 40th to Highway 2

Pavement Repair Project

Construction will include repairing or replacing deteriorated concrete panels and curbs, sealing joints and cracks and milling the concrete surface before overlaying with asphalt. Other work will include the replacement of damaged storm drainage inlet tops, utility adjustments and restoration of traffic signal elements impacted by the work.

  • Project Start: Apr 26, 2017
  • Completion: Mid-Nov 2017

Go

Superior from 27th to Cornhusker

Concrete Pavement Repair Project

The project consists of replacing and/or repairing concrete panels, joints, median surfacing, curbs, and curb inlets within the street that are deteriorated. Areas of the project with asphalt paving will be replaced with full depth concrete.

  • Project Start: Apr 17, 2017
  • Completion: Nov 4, 2017

Go

Yankee Hill from 70th to Highway 2

Road Reconstruction and Widening Project

The project includes paving Yankee Hill from 70th Street to Highway 2, widening it to four lanes between Sutherland Street and Highway 2 and building roundabouts at the quarter-mile, half-mile and mile intersections.

  • Project Start: Summer 2016
  • Completion: Fall 2017

Go

Related Information