Public Works & Utilities Construction Projects

Project start and completion dates are estimates. Information subject to change.

10th and Salt Creek Bridge Project

10th & Salt Creek Bridge

Bridge Replacement Project

A recent structural evaluation has determined that the bridge would need to be replaced in order to meet the City of Lincoln's current and future vehicular and pedestrian needs. This project will include removing the existing bridge and constructing a new bridge at the current location.

  • Start: May 8, 2017
  • Completion: Mid-2018

Go

14th and Superior Roundabout

14th and Superior

Permanent Safety Improvements

This project includes replacing the temporary traffic control changes at the 14th and Superior roundabout with more permanent traffic control features. Thanks to a public-private partnership, the total investment will not only include concrete, turf, and trees, but also live plants, native grasses and other decorative items.

  • Start: May 2, 2017
  • Completion: Late-Jul. 2017

Go

16th Street from "A" to "F"

Roadway Reconstruction Project

This project provides much needed road repairs and will improve conditions of 16th St. between "A" and "F" streets.

  • Start: Mar 1, 2017
  • Completion: Aug. 2017

Go

27th from Holdrege to Fletcher

Concrete Pavement Repair Project

The project consists of replacing and/or repairing concrete panels, joints, median surfacing, curbs, and curb inlets within the street that are deteriorated. Areas of the project with asphalt paving will be replaced with full depth concrete.

  • Start: Apr 17, 2017
  • Completion: Nov. 2017

Go

27th and Woods Area

Water Main Replacement/Water Service Relocation Projects

The scope of this work will involve the abandonment of existing water mains, the installation of a new water main on Woods Boulevard near 27th Street, and a new main on the north side of Calvert Street across 27th Street.

  • Start: Mar 5, 2017
  • Completion: 6-8 weeks

Go

33rd from Holdrege to Madison

Mill, Overlay and Storm Drainage Improvements

The planned construction will include repairing or replacing deteriorated concrete base, curb, milling and replacing the asphalt surface. Other work includes replacing damaged storm drainage structures and inlet tops, impacted sidewalks, and reconstructing curb ramps.

  • Start: Jun. 19, 2017
  • Completion: Mid-Oct. 2017

Go

NW 48th from W Vine to W Adams

Roadway Project

NW 48th Street will be constructed as a four-lane divided road between W Holdrege Street and Highway 34. South of W. Holdrege Street, the road has been designed as a six-lane road to match NDOR’s interchange project, though only five lanes are being built now.

  • Start: Mar 2015
  • Completion: Nov. 2016

Go

Cleveland from Cotner to Leonard

Water Main Replacement Project

The City of Lincoln proposes to replace the existing water main along Cleveland Street from Cotner Blvd. to Leonard St. This project is necessary to reduce costly water main breaks and provide customers with better water service in the area.

  • Start: Mar 27, 2017
  • Completion: 7 weeks

Go

Coddington and West Van Dorn

Safety Improvement Project

The purpose of this project is to reduce vehicle crashes by significantly reducing the number of conflict points at the intersection. A single-lane roundabout will be constructed within the intersection. The project includes the phased construction of new concrete pavement, trails, sidewalks and box culvert extensions; the installation of a new storm drainage system; and new signage, pavement markings and street lighting.

  • Start: Apr 24, 2017
  • Completion: Oct 2017

Go

Fremont from Touzalin to 70th

Water Main Replacement Project

This project will replace the water main along Fremont Street from Touzalin to 70th.

  • Start: May 15, 2017
  • Completion: Sep. 2017

Go

Nance and “D” Area

Water Main Replacement Projects

The Public Works and Utilities Department began two water main replacement projects in February 2017: Nance Avenue from 8th to 12th streets and “D” Street from 12th to 20th streets.

  • Start: Feb 20, 2017 / Feb 27, 2017
  • Completion: 12 weeks / 24 weeks

Go

Old Cheney from 40th to Highway 2

Pavement Repair Project

Construction will include repairing or replacing deteriorated concrete panels and curbs, sealing joints and cracks and milling the concrete surface before overlaying with asphalt. Other work will include the replacement of damaged storm drainage inlet tops, utility adjustments and restoration of traffic signal elements impacted by the work.

  • Project Start: Apr 26, 2017
  • Completion: Mid-Nov 2017

Go

Superior from 27th to Cornhusker

Concrete Pavement Repair Project

The project consists of replacing and/or repairing concrete panels, joints, median surfacing, curbs, and curb inlets within the street that are deteriorated. Areas of the project with asphalt paving will be replaced with full depth concrete.

  • Project Start: Apr 17, 2017
  • Completion: Nov 4, 2017

Go

Yankee Hill from 70th to Highway 2

Road Reconstruction and Widening Project

The project includes paving Yankee Hill from 70th Street to Highway 2, widening it to four lanes between Sutherland Street and Highway 2 and building roundabouts at the quarter-mile, half-mile and mile intersections.

  • Project Start: Summer 2016
  • Completion: Fall 2017

Go

Related Information