West Fletcher Avenue and Highway 34 Safety Improvement Project

August 29, 2018

Project Overview

This project includes construction of two right-turn lanes and street resurfacing in the area of W Fletcher Avenue and Highway 34. The turning lanes are designed to increase safety and improve efficiency at the intersection. Resurfacing will take place along W Fletcher Ave between Highway 34 and N 1st Street to fix and prevent potholes and cracks. Other improvements include adding ADA-accessible sidewalks and upgrading street lights.

Access During Construction

Traffic will be maintained in all directions during turn lane construction. Motorists will be advised of periodic lane closures as required. During resurfacing on W Fletcher Avenue, traffic will be shifted into a head-to-head configuration, allowing the contractor to perform work on one side of the street while traffic is maintained on the other.

Schedule

Construction is anticipated to begin September 4, 2018, and the project is scheduled to be completed by November 2018.

Project Contact

  • James Puls, Construction Project Manager

    City of Lincoln, Public Works
    Phone: 402-525-5641
    Email: jpuls@lincoln.ne.gov

  • Marc Rosso, Project Engineer

    City of Lincoln, Public Works
    Phone: 531-207-3244
    Email: mrosso@lincoln.ne.gov

  • Mike McCullough, Project Superintendent

    MTZ Construction
    Phone: 402-470-1176