Cotner from Fairfax to Leighton

September 25, 2013

The City of Lincoln proposes to mill and overlay North Cotner Boulevard from Leighton Avenue to Fairfax Street beginning on October 7, 2013, weather permitting. The existing asphalt pavement will be milled off and overlaid with new asphalt and pavement markings. Pedestrian curb ramps will be reconstructed to meet ADA standards.

Pavers Inc. will be the contractor. They will perform the work under a total street closure with the road closed to through traffic. Traffic from Cotner Boulevard will be detoured to 70th Street along Holdrege Street and Adams Street. Access to side streets and driveways will be restricted at times during the construction operations. The Contractor and the City will work with local businesses and residences regarding access during construction.

If a business or residence has a sprinkler system in close proximity to the existing curb ramps, they are asked to flag the sprinkler heads to aid the contractor in minimizing damage.

◄ Back to Construction Updates