Connection to the west end of tunnel underneath the BNSF tracks
Backfill operations at the connection of Salt Valley Trunk Sewer Phase IV and Beal Slough
Dairy Hill initial soil removal - looking east toward 14th Street.
Tunneling pit
Project Background
Phase I is the first phase of a multi-phased and multiyear project for providing additional capacity necessary to meet current and future growth in the Beal Slough basin. This relief trunk sewer adds 60-inch, 36-inch, and 30-inch diameter piping that runs parallel to an existing line.
Project Summary
- Project Information:
- 605 LF of 60-inch diameter sewer
- 3,617 LF of 36-inch diameter sewer
- 5,473 LF 30-inch diameter sewer
- 550 LF of 27-inch diameter sewer
- Roadway crossings at 14th Street, Southwood Drive, and 27th Street to be tunneled. No disruption to the traveling public.
- Total Project Cost: $ 6,925,000 (Estimated)
- Construction Contract Cost: $5,725,416.20
- Funding: Sanitary Sewer Revenue Funds
Construction Status - Complete
- Substantial Completion: July 2007
- Final Completion: December 2007
Project Contacts
- Construction Contractor
- Garney Companies, Inc.
- Mike Atkinson, (816) 746-7213
- Lincoln Wastewater System
- Brian Kramer
- Supt. Wastewater Collection and Project Manager
- bakramer@lincoln.ne.gov, (402) 441-7961
- Olsson Associates (Consulting Engineer)
- Holly Johnson
- Project Engineer
- hjohnson@oaconsulting.com, (402) 474-6311
- Randy Moses
- Construction Observer
- rmoses@oaconsulting.com, (402) 474-6311