Upper Beal Slough Sanitary Trunk Sewer Extension - Project No. 700924

The project connects to an existing 27 inch diameter trunk near So. 60th & Pine Lake Road and then continues southeasterly to So. 70th St. and Yankee Hill Road. This line will provide service for future growth in the upper reaches of the Beal Slough Basin south of Pine Lake & Yankee Hill Roads and east and west of So. 70th St.

Construction included video television inspection, testing of manholes and piping, open trenching along 70th St. S. and through Yankee Hill Road, and restoring of top soil

Click for larger view
Tunneling – Railroad Undercrossing

Project Summary

General:
     Trunk Sewer Pipe24 inch diameter – 5,350 LF
18 inch diameter - 790 LF
     Tunneled Pipe Casing:36 inch diameter - 475 LF
Total Project Cost:$1,600,000 (Estimated)
Project Construction Cost:$1,018,710
Construction Status:Complete
Funding:Sanitary Sewer Revenue Funds

Project Schedule

Start of ConstructionOctober 29, 2007
Substantial CompletionApril, 2008
Final CompletionMay, 2008

Project Contacts

L.G. Roloff Construction Co. Inc. (Construction Contractor):

  • Bob Norris – Project Manager
  • (402) 861-1721

EA Engineering, Science, & Technology Inc.

Lincoln Wastewater System: