2005 Stormwater Bond Issue: Public Meetings

69th Street and Walker Avenue Open House


Construction Map
Thursday, January 26, 2006
5:00-6:30 p.m.
(Presentation at 5:30)
Anderson Branch Library
Location Map
3635 Touzalin Avenue

You are invited to attend the second of two Open House events planned to discuss the stormwater drainage improvements for the 69th and Walker drainage area. The proposed design has taken into account the comments/suggestions received during the first open house meeting held on September 14, 2005. JEO Consulting Group, Inc. is working with the City on the design of this project. Construction on this project will begin in the Summer of 2006 and is anticipated to be completed by the Fall of 2006. The project staff will be available for one-on-one conversation to answer your questions and tell you what to expect during construction.