21st Street Stormwater Bypass System
- Contact Person:
- Ben Higgins
- 402-441-7589
- Type of Project:
- Construction
- Urban Storm Drain Project
- Description:
- Approximately five blocks of a large, new storm drainage pipe project near 21st Street Corridor, from 'N' to 'S' Street. This project is being constructed in conjunction with the Antelope Valley Project. This phase is the second of four phases and will capture storm drainage from the west side of Antelope Creek and relay it downstream to an outlet near 'R' Street.
- Project Status:
- Construction Complete
- Consultant:
- Olsson Associates
- Contractor:
- Hawkins Construction
- Photos:
- Construction:

Construction on 21st St.
New Pipe
Abutment footing for new bridge
November 2006
Pier footing pilings for new bridge- Construction Complete:

- Map of Project:
- Download Project Map (296 K)

- Download Project Map (296 K)
- Lincoln Journal Star Article: "Work begins on P, Q streets' Antelope Valley bridges"