2005 Stormwater Bond Issue

28th and Fair


28th & Fair Area Improvements

Contact Person:
Kent Evans
402-416-4552
Type of Project:
Design and Construction
Urban Storm Drain Project
Description:
The existing storm drainage system is outdated, cannot handle heavy stormwater flows, and experiences street flooding during heavy rain events. The solution is to build a new underground storm drainage system that will route the existing flow to a larger nearby stormwater system that can better handle this amount of stormwater runoff.
Project Status:
Construction Complete
Consultant:
Olsson Associates
Contractor:
Skoda Construction
Video:
Photos:
Alley flooding prior to construction:

Between 27th & 28th and Fair & Potter

Between 27th & 28th and Fair & Potter
Flood damage at apartment adjacent to alley:
Construction:

August 2007

August 2007
Construction Complete:

September 2007
Map of Project:
Public Meetings:
January 24, 2006:
November 14, 2006: Meeting Notice