38th & Sewell Area Improvements
- Contact Person:
- Craig Aldridge
- 402-416-5349
- Type of Project:
- Design and Construction
- Urban Storm Drain Project
- Description:
- The storm drain system in this area is too small to handle rain from larger storms which results in street flooding. The solution is to build a new stormwater drainage system along side the existing underground stormwater system. The added system will reduce street flooding in this area.
- Project Status:
- Construction Complete
- Consultant:
- E&A
- Contractor:
- Skoda Construction
- Video:
- Download Project Video (1:39)

- Download Project Video (1:39)
- Photos:
- Construction:

July 2006
July 2006
July 2006- Map of Project:
- Download Project Map (309 K)

- Download Project Map (309 K)
- Public Meetings:
- October 13, 2005
- February 2, 2006: Meeting Notice
- May 24, 2006: Meeting Notice