- Description:
- The existing stormwater trunk main along 2nd Street between 'N' and 'O' streets does not have enough capacity to accommodate the appropriate design-year storm. As a result, a secondary main was constructed along 2nd Street between 'N' and 'O' streets.
- Project Status:
- Construction Complete
- Consultant:
- The Schemmer Associates
- Contractor:
- Cramer & Associates