This project widened South Folsom Street to accommodate turning traffic into Foxtail Meadows. Other work included storm drainage improvements and street resurfacing. Additional improvements included extensions of the existing pipe culverts in areas where South Folsom Street was widened, and a mill and overlay of South Folsom Street with base repairs where required.
Lincoln on the Move funding was utilized in accordance with ballot language and supported by the Advisory Committee on Transportation (ACT).
Construction took place in 2023.
Randy Saathoff, City Construction Project Manager City of Lincoln, LTU Project Delivery rsaathoff@lincoln.ne.gov 402-440-6067
Russ Gasper, Construction Engineer City of Lincoln, LTU Project Delivery rgasper@lincoln.ne.gov 402-580-8438