Lincoln Area Bridge Preventative Maintenance Project

Project Summary

This project will include an assessment and construction of the appropriate maintenance treatment for bridges at six locations throughout the city. Bridges include:

  • “O” Street viaduct (Harris Overpass)
  • 27th Street viaduct
  • SW 40th Street viaduct
  • Sheridan Blvd. Penny Bridges
  • 37th and South streets
  • 10th and Salt Creek bridge

The improvements on this project would consist of bridge rehabilitation, including deck patching and overlays, joint replacement, approach slab repairs, rail repairs, and sidewalk repairs.

Project information sheet  Hoja informativa del proyecto 

Project Location

Funding

Schedule

Construction is anticipated to take place in 2027.

Access During Construction

The project would be constructed under traffic with lane closures controlled by appropriate traffic control devices and practices; however, closures would be required to accommodate work on the Penny Bridges. Closures may also be required to accommodate work on other bridge locations.

Potential Detour Routes 

Project Contact