56th Street from Spruce Street to Van Dorn Street Street Rehabilitation Project

March 2020

Purpose and Need

The purpose of this project is to preserve the transportation asset, improve the reliability of Lincoln’s transportation system, and ensure the mobility of the traveling public. The need for this proposed project is based on the condition of the existing pavement.

Scope of Work

This proposed project would rehabilitate the pavement along 56th St. from Spruce St. to Van Dorn St. to improve roadway conditions as necessitated by the current pavement age and condition.

Right of Way

Acquisition of right-of-way is not anticipated for this project.

Project Schedule

Design

The City is in the process of selecting a consultant for design of this project. Design is anticipated to begin in fall of 2020.

Construction

Construction is tentatively planned to occur in late spring and summer 2023 and be completed in fall 2023. Construction phasing will be determined during the design phase.

  • Project Area

Re-center mapFull-screen

Project Contacts

Please contact the City of Lincoln with any questions, comments, or concerns you would like to share regarding the proposed project.

  • Kris Humphrey, Design Project Manager

    City of Lincoln, LTU Project Delivery
    Engineering Design Section
    Email: khumphrey@lincoln.ne.gov
    Phone: 402-326-1176