Purpose and Need

The purpose of this project is to preserve and extend the service life of existing facilities. The improvements would satisfy existing and future traffic needs and conditions in a manner conducive to safety, durability, and economy of maintenance. The need of the project is to address substandard and aging traffic signal infrastructure as well as address substandard curb ramps.

Scope of Work

This project would replace traffic signal poles and related infrastructure at the intersection of 84th Street and College Park Drive. Curb ramps would be reconstructed to meet current standards.

Project Schedule

Construction is tentatively planned to occur in 2022.

  • Project Area

Re-center mapFull-screen

Project Contact

  • Danielle Vachal, Design Project Manager

    City of Lincoln, LTU Project Delivery
    Engineering Design Section
    Email: dvachal@lincoln.ne.gov
    Phone: 531-289-8211