56th from Vine to Adams Street Rehabilitation Project

Updated May 2018

Scope of Work

The project’s street improvements will include mill and overlay of the existing asphalt, pavement repairs, joint sealing and new pavement markings. Pedestrian curb ramps will be reconstructed to meet federal and local standards.

Schedule

The project is scheduled to begin May 21, 2018. The street is expected to open to traffic in early August.

Access During Construction

Traffic will be maintained in both directions while the sidewalk ramps are under construction. Work will begin with a southbound lane closure from Adams to Garland for sidewalk ramp reconstruction.

During the mill and overlay (resurfacing) operations, expect phased lane closures that maintain traffic in at least one direction at all times. In response to citizen input, the 56th and Holdrege intersection will be temporarily closed on a Monday during off peak hours to complete the mill and overlay before business hours the next day. The 56th and Leighton intersection will also be closed during off peak hours to complete the joint sealing. The intersections will not be closed at the same time. Message signs will be used for advance notification of any intersection or lane closures.

  • Project Area

Full-screen

Public Involvement

Pre-construction Open House – April 26, 2018
5:30 – 6:30 p.m.
Lincoln Lutheran High School, 1100 N 56th
Open House Handout PDF Open House Invitation PDF
Project Information Mailer - February 2018  (174 K) PDF

Project Contact

  • Jess Sundeen, Construction Project Manager

    City of Lincoln, Engineering Services
    Phone: 402-416-5341
    Email: jsundeen@lincoln.ne.gov

  • Erin Sokolik, Project Engineer

    City of Lincoln, Engineering Services
    Phone: 402-416-9460
    Email: esokolik@lincoln.ne.gov

  • Mike McCullough, Construction Project Manager

    MTZ
    Phone: 402-904-5085
    Email: mike.mtzllc@gmail.com